Ngā whakapai ārai waipuke o East Coast

East Coast flood resilience improvements

Following the impacts of Cyclone Gabrielle in February 2023, along with previous significant flood events, flood resilience options have been investigated for the East Coast communities of Ūawa (Tolaga Bay), Tokomaru Bay, Mākarika and Tikitiki.

The project focuses on cost-effective solutions to reduce flood risk to 38 homes, as well as community facilities and critical infrastructure. Technical investigations, engagement with mana whenua and communities and assessment of a wide range of flood mitigation options have helped identify preferred approaches for each catchment.

Project status update - November 2026

Stage 1 investigations and community engagement have now been completed across the East Coast catchments. Between mid-2024 and June 2026, around 42 hui and engagement meetings were held with iwi, hapū, communities and flood focus groups to help identify preferred flood resilience options.

In June 2026, Council endorsed a programme-wide framework to prioritise flood resilience investment across Tairāwhiti, based on flood risk reduction, affordability, available funding and delivery feasibility.

Council has endorsed the preferred projects to progress to Stage 2 design and consenting, subject to Crown funding approvals. The updates below outline the preferred options, project status and next steps for each East Coast catchment.

On this page

Tikitiki - Poroporo River

Stage 1 investigations found that flood risk to Tikitiki township and Tikitiki School is mainly driven by rising riverbed levels, channel movement and overbank flooding.

  • The preferred option includes upgrading and extending the existing stopbank behind Tikitiki School, alongside rock erosion protection at the river bend and minor stormwater improvements.
  • The preferred option met Crown funding requirements and will progress to Stage 2 design and consenting.
  • Longer-term measures including an overflow or diversion channel and further stopbank raising, may be considered through future adaptation planning as river conditions change.
  • The Stage 1 findings and next steps were discussed with the community at a hui in October 2026. Tikitiki Update Presentation

Tokomaru Bay

Stage 1 investigations assessed flood risk and potential mitigation options for both the Mangahauini River and Waiotu Stream.

  • For the Mangahauini River, the preferred option includes widening and strengthening the existing stopbank upstream of the SH35 bridge, with minor height increases and a review of existing rock erosion protection.
  • For Waiotu Stream, the preferred option includes flood protection bunds around Hatea-A-Rangi School and widening sections of the stream channel to help reduce flood risk and road raising Arthur Street.
  • The Mangahauini River works and Waiotu Stream improvements around Hatea-A-Rangi School met Crown funding requirements and will progress to Stage 2 design and consenting.
  • The proposed Arthur Street stopbank and road raising did not meet Crown funding requirements and will not progress at this stage.
  • The Stage 1 findings and next steps were discussed with the community at a hui in October 2026. Tokomaru Bay Update Presentation

Ūawa / Tolaga Bay

Stage 1 investigations and flood modelling show that, under the current climate conditions, most of Tolaga Bay township is unlikely to flood from the Ūawa River during a flood that has a 1% chance of occurring in any given year. However, climate change is expected to increase flood risk, particularly on the western side of the township.

  • A new stopbank northwest of the township, between SH35 and the Ūawa River, has been identified as the preferred option to help reduce future flood risk.
  • Flood modelling shows the proposed stopbank could protect around 50 homes during a future flood event, taking into account the effects of climate change.
  • The preferred option meets Crown funding requirements and will move to Stage 2 design and consenting, including confirmation of the stopbank alignment.
  • Funding for construction has not yet been confirmed. This may need to be considered through the Long Term Plan or future funding opportunities.
  • The Stage 1 findings and next steps were discussed with the community at a hui in October 2026. Ūawa Update Presentation

Mākarika

Stage 1 investigations show that large amounts of sediment are building up in the stream, causing the stream bed to rise. This increases the risk of flooding and the stream changing course towards the settlement.

  • A stopbank close to the stream was investigated as a possible short-term option to reduce flood risk.
  • Due to ongoing sediment build-up, the proposed stopbank is expected to be effective for only 10 years or less, with limited longer-term benefits.
  • The proposed stopbank did not meet Crown funding requirements and will not progress to Stage 2 design and consenting at this stage.
  • Council will continue working with the community, Civil Defence Emergency Management and the Ministry of Education on longer-term responses. These include community-led managed retreat, improved flood warnings and emergency planning, future road and bridge options and targeted nature-based solutions where these are found to be effective.
  • The Stage 1 findings and next steps were discussed with the community at a hui in October 2026. Mākarika Update Presentation